Classroom Construction - Week 1
Posted on Monday, 30 August 2010, 9:12 a.m.   Print Article
Caption: Clearing the building siteClearing the building site

Week 1

The construction of our new 8 classroom block is now underway.    On Monday morning we arrived at school to find construction signs, barriers, fencing and blue netting around the building site.   A site office and digger have also made this area their new home.

The digger has been busy cutting up concrete and clearing the site of the rubble the was left behind after the two classrooms were removed during the Xmas holidays.   This extremely noisy work made us appreciate how far Room 19 is from the construction site.

Wooden profiles and orange spray paint mark out the new building's outline and a large truck delivered metal which has been spread around to form a good base for the next stage.  On Thursday afternoon we thought we were having a fire drill when the alarm bells began and continued to do so for quite some time.   We found out later that a digger had cut through some wiring.

Report constructed by Georgia L, Aaron, Emily, Elijah, Tori and Tyla of Room 19.

Other Articles:
February , 2013
Environmental Education
January , 2013
Visiting Students from New Caledonia
October , 2012
Speech Finals.
Westpac Helicopter
August , 2012
Learning to draw with Graham Braddock
Mini Olympics
June , 2012
Rebuilding Christchurch
Art Gallery Visit
Ronald McDonald's Road Safety Visit.
October , 2011
Nominations are now being called ...
April , 2011
Official Opening of New Building
January , 2011
School Uniform
November , 2010
Classroom Construction - Week 12
Classroom Construction - Week 11
Classroom Construction - Week 10
Classroom Construction - Week 9
October , 2010
Classroom Construction - Week 8
Classroom Construction - Week 5
Classroom Construction - Week 4
Classroom Construction - Week 3
12